Nash pool to be closed for repairs

Posted

OREGON – Nash Recreation Center Pool will be closed for repairs beginning April 15th.

 Following the pool closure in August 2021 to repaint the pool surface, staff identified the paint was not adhering to the pool’s surface. This was communicated with the contractor and the contractor will be returning to complete the corrective work. The work will not result in any additional fees outside the originally contracted amount. 

“The district is fortunate to have discovered the issue early on and has worked alongside the contractor to identify a solution.” said Erin Folk, Executive Director.

The pool closure is expected to last four weeks to allow for proper cure time of the primer and paint prior to refilling the pool. During this time the district will also complete routine maintenance and a deep cleaning of the locker rooms and pool deck. The closure will take the place of the Oregon Park District’s regularly scheduled closure in August.

The pool is anticipated to reopen on May 16th but will reopen sooner if the corrective work is completed sooner than expected. All Water Aerobic passes will automatically be extended for the duration of the pool closure. All other members that will not be utilizing Nash Recreation Center during the pool closure may temporarily suspend their pass. The temporary suspension will extend their membership for the duration of the pool closure.  To request a pass suspension, please contact the front counter receptionist at 815-732-3101.